Aside section
Cases

INTERPIPE reduced equipment downtime by 30% thanks to SmartEAM from IT-Enterprise
Implementation of IT-Enterprise EAM system let Interpipe holding to reduce maintenance costs, carry out production equipment repairs based on information about their current condition, ensure high reliability of equipment operation with preventive repairs where failure probability becomes high.

"Rivne High-Voltage Equipment Plant" reduced the TVC by 40-60% for all types of products thanks to IT-Enterprise
Rivne plant of high-voltage equipment reduced the manufacturing lead time of orders by 40-60% with the IT-Enterprise ERP system implementation

"Rivne High-Voltage Equipment Plant" implemented accurate online product cost planning together with IT-Enterprise
Thanks to the implementation of the IT-Enterprise system, operational control of direct cost is provided in real-time. Due to this, a deviation of the actual cost of production from planned to an amount not exceeding 1%.